Saint Peter Antiochian Orthodox Church
Madison, Mississippi
Friday, August 31, 2007
Building Progress 8/31/07
Still waiting on the electrician to move the breaker box in the hallway before they can finish the sheet-rocking in the hallway and  kitchen The vestry is being sheet-rocked today.   The new office has received its first coat of paint on the rest of the walls and the trim.  The paint in the hallway and bathrooms is an attractive off-white or cream color.  There will also be an accent wall in the bathroom, but that color hasn't been finalized yet.  The new office is a pretty blue-gray.  They are waiting on the granite for the vanity in the bathroom before they begin installing the fixtures there.  The stalls have been put in place in both bathrooms.  Today they have started laying the cement blocks for the walls for the new narthex and bell tower.  They have also laid the forms for the replacement sidewalk for the one that was previously torn up beside the church.   Soon they will be preparing the ground for the patio which will go in front of the fellowship hall.  God has been very gracious to us during this process.  Please continue to pray for our parish.
posted by Daniel Root at 1:57 PM Parish Life
Concrete is down!

More pictures soon.
posted by Daniel Root at 1:38 PM Parish Life
Tuesday, August 28, 2007
Pictures from Teen Meeting 8/26/07
posted by Daniel Root at 7:39 PM Parish Life
Wednesday, August 15, 2007
Building progress - August 15th 2007
Sheet-rocking is almost complete in the hallway, new office, new vestry and kitchen. They are waiting on the electrician to move the breaker box in the hallway before they can finish the sheet-rocking.   The tile floor has been laid in the new bathrooms and they are adding the grout today.  Once the flooring is finished in the bathrooms, they will finish painting them and install the fixtures.  The vanities will be a beautiful granite.  There will also be changing tables for infants.  The ground is being prepared out front for the new narthex, bell tower and the front porch for the church itself.  Soon they will be putting the forms in place and pouring the concrete there.  God has been very gracious to us during this process.  Please continue to pray for our parish.
posted by Daniel Root at 4:27 PM Parish Life
Wednesday, August 08, 2007
Building progress - August 8th 2007
Sheet-rocking is almost complete in the hallway, new office, new vestry and kitchen.  The ceilings in the new bathrooms are being stippled and the first coat of paint has gone on today.  The sidewalk beside the church and in the area of the old front porch have been removed.  Once painting is finished, new carpet will be installed in the hallway and office.  Soon the flooring in the new bathrooms and the kitchen will be going down and the plumbing fixtures for the new bathrooms will be set in place.  They will also begin the groundwork for the circular cobblestone patio that will go in front of the fellowship hall.  God has been very gracious to us during this process.  Please continue to pray for our parish.
posted by Daniel Root at 10:05 AM Parish Life
 